New development may derail Prasarana-SEB settlement plan

Posted on
Share this article   

PETALING JAYA: A new disagreement between Prasarana Malaysia Bhd and Scomi Engineering Bhd (SEB) is threatening to derail their plan to settle the RM494mil monorail contract dispute out of court.

In a filing with Bursa Malaysia yesterday, SEB said Prasarana claimed that the third supplemental contract (TSC), aimed at amicably determining the legal proceedings between the parties, had automatically lapsed and become null and void.

Under the TSC, Prasarana and SEB’s unit Scomi Transit Projects Sdn Bhd (STP), which had earlier gone to court over the dispute, had agreed to jointly appoint an independent consultant to determine STP’s claims and Prasarana’s claims under the contracts arising prior to June 23, 2016.

Prasarana, in a letter to STP on May 3, said that the last condition precedent under the TSC had not been fulfilled within the stipulated period, ie, within 21 days from the TSC’s date or any extension not exceeding 40 days from the date of expiry of the original conditions precedent period.

The condition precedent that was not met, as claimed by Prasarana, was the execution by STP’s financiers of a deed of reassignment and revocation that unconditionally and irrevocably revokes the assignment of contract proceeds dated May 30, 2011.

“This was despite STP’s stance that they do, in fact, consider that there has been, by provision of the letter from STP’s financiers, compliance with the terms of TSC and/or the last condition precedent,” said SEB.

Subsequent to Prasarana’s letter, Prasarana and STP continued to discuss the status of satisfaction of the last condition precedent in the presence of third parties, including STP’s financiers.

SEB said this had resulted in STP officially providing certain additional documents to Prasarana on May 16 with regard to the issue, acting on advice and request.

STP is now awaiting Prasarana’s response on the status of the last condition precedent.

SEB said the board would continue to provide updates from time to time on any material developments.

The contract at the centre of the Prasarana-STP dispute involves the upgrading of the Kuala Lumpur monorail stations and the electrical and mechanical system, the construction of a new depot, and delivery of 12 sets of new four-car trains.

 

Want to contribute articles to StarProperty.my? Email: editor@starproperty.my
Related News

Fresh from the news oven

15:01 PM
News & Articles
15:07 PM
Featured
10:05 AM
Property News
Latest News

Stories and news that might pique your interest

21:11 PM
News & Articles
16:11 PM
News & Articles
14:11 PM
News & Articles
13:11 PM
News & Articles
21:11 PM
News & Articles
16:11 PM
News & Articles
14:11 PM
News & Articles
13:11 PM
News & Articles
21:11 PM
News & Articles
16:11 PM
News & Articles
14:11 PM
News & Articles
13:11 PM
News & Articles
21:11 PM
News & Articles
16:11 PM
News & Articles
14:11 PM
News & Articles
13:11 PM
News & Articles
16:08 PM
Home & Living
09:08 AM
Home & Living
11:02 AM
Home & Living
09:08 AM
Home & Living
10:07 AM
Home & Living
12:07 PM
Home & Living
00:11 AM
Featured Dev
00:11 AM
Featured Dev
00:11 AM
Featured Dev
01:10 AM
Featured Dev
00:08 AM
Events
19:05 PM
Events
18:05 PM
Awards 2024
16:05 PM
Events
15:05 PM
Events
00:10 AM
Awards 2024
09:04 AM
News & Articles
16:03 PM
News & Articles
10:02 AM
News & Articles
11:11 AM
News & Articles
11:09 AM
Featured
11:11 AM
Investment
16:06 PM
Investment
16:06 PM
Featured
15:06 PM
Investment
12:07 PM
潮樓產業
14:07 PM
潮樓產業
10:07 AM
潮樓產業
16:07 PM
潮樓產業
14:07 PM
潮樓產業
12:07 PM
潮樓產業